3/7968
06/08/2023 20:29
06/08/2025 20:29
ODP HECTOR INTL, FARGO, ND.
TAKEOFF MINIMUMS AND (OBSTACLE) DEPARTURE PROCEDURES AMDT 4A...
TAKEOFF OBSTACLE NOTES: RWY 9: LIGHT POLE, SIGN BEGINNING 10 FT
FROM DER, 70 FT LEFT OF CENTERLINE, UP TO 2 FT AGL/900 FT MSL.
LIGHT POLE, UTILITY BUILDING BEGINNING 40 FT FROM DER, 89 FT RIGHT
OF CENTERLINE, UP TO 3 FT AGL/901 FT MSL.
UTILITY BUILDING 41 FT FROM DER, 90 FT LEFT OF CENTERLINE, 3 FT
AGL/901 FT MSL.
TRAVERSE WAYS BEGINNING 419 FT FROM DER, 601 FT RIGHT OF
CENTERLINE, UP TO 913 FT MSL.
POLE 1034 FT FROM DER, 683 FT LEFT OF CENTERLINE, 40 FT AGL/939 FT
MSL.
POLES BEGINNING 1041 FT FROM DER, 467 FT RIGHT OF CENTERLINE, UP TO
40 FT AGL/938 FT MSL.
TREE 1851 FT FROM DER, 990 FT LEFT OF CENTERLINE, 49 FT AGL/948 FT
MSL.
TREES BEGINNING 1874 FT FROM DER, 689 FT LEFT OF CENTERLINE, UP TO
66 FT AGL/965 FT MSL.
TREE 1950 FT FROM DER, 994 FT RIGHT OF CENTERLINE, 54 FT AGL/948 FT
MSL.
TREES BEGINNING 2591 FT FROM DER, 1100 FT RIGHT OF CENTERLINE, UP
MSL.
END PART 1 OF 3
ODP HECTOR INTL, FARGO, ND.
TO 74 FT AGL/969 FT MSL.
RWY 18: LIGHT POLE 4 FT FROM DER, 95 FT RIGHT OF CENTERLINE, 2 FT
AGL/900 FT MSL.
LIGHT POLES BEGINNING 5 FT FROM DER, 54 FT LEFT OF CENTERLINE, UP
TO 2 FT AGL/900 FT MSL.
LIGHT POLES, SIGN BEGINNING 9 FT FROM DER, 33 FT LEFT OF
CENTERLINE, UP TO 2 FT AGL/901 FT MSL.
LIGHT POLES BEGINNING 10 FT FROM DER, ON AND RIGHT OF CENTERLINE,
UP TO 2 FT AGL/901 FT MSL.
TRAVERSE WAY 536 FT FROM DER, 19 FT RIGHT OF CENTERLINE, 914 FT
MSL.
RWY 27: TRAVERSE WAYS, UTILITY BUILDING BEGINNING 9 FT FROM DER, 39
FT LEFT OF CENTERLINE, UP TO 1 FT AGL/897 FT MSL.
TRAVERSE WAYS, LIGHT POLE, SIGN BEGINNING 10 FT FROM DER, 50 FT
RIGHT OF CENTERLINE, UP TO 2 FT AGL/897 FT MSL.
UTILITY BUILDING 40 FT FROM DER, 125 FT RIGHT OF CENTERLINE, 4 FT
AGL/898 FT MSL.
TRAVERSE WAY BEGINNING 449 FT FROM DER, 478 FT RIGHT OF CENTERLINE,
UP TO 910 FT MSL.
TREE 2911 FT FROM DER, 943 FT LEFT OF CENTERLINE, 971 FT MSL.
MSL.
END PART 2 OF 3
ODP HECTOR INTL, FARGO, ND.
RWY 36: LIGHT POLE, TRAVERSE WAYS, ELECTRICAL SYSTEM, POLE
BEGINNING 9 FT FROM DER, 55 FT RIGHT OF CENTERLINE, UP TO 1 FT
AGL/901 FT MSL.
LIGHT POLES, TRAVERSE WAYS BEGINNING 9 FT FROM DER, 54 FT LEFT OF
CENTERLINE, UP TO 2 FT AGL/901 FT MSL.
TREE 2067 FT FROM DER, 984 FT LEFT OF CENTERLINE, 62 FT AGL/954 FT
MSL.
END PART 3 OF 3
Start Date UTC
06/08/2023 20:29
End Date UTC
06/08/2025 20:29
Conditions
ODP HECTOR INTL, FARGO, ND.
TAKEOFF MINIMUMS AND (OBSTACLE) DEPARTURE PROCEDURES AMDT 4A...
TAKEOFF OBSTACLE NOTES: RWY 9: LIGHT POLE, SIGN BEGINNING 10 FT
FROM DER, 70 FT LEFT OF CENTERLINE, UP TO 2 FT AGL/900 FT MSL.
LIGHT POLE, UTILITY BUILDING BEGINNING 40 FT FROM DER, 89 FT RIGHT
OF CENTERLINE, UP TO 3 FT AGL/901 FT MSL.
UTILITY BUILDING 41 FT FROM DER, 90 FT LEFT OF CENTERLINE, 3 FT
AGL/901 FT MSL.
TRAVERSE WAYS BEGINNING 419 FT FROM DER, 601 FT RIGHT OF
CENTERLINE, UP TO 913 FT MSL.
POLE 1034 FT FROM DER, 683 FT LEFT OF CENTERLINE, 40 FT AGL/939 FT
MSL.
POLES BEGINNING 1041 FT FROM DER, 467 FT RIGHT OF CENTERLINE, UP TO
40 FT AGL/938 FT MSL.
TREE 1851 FT FROM DER, 990 FT LEFT OF CENTERLINE, 49 FT AGL/948 FT
MSL.
TREES BEGINNING 1874 FT FROM DER, 689 FT LEFT OF CENTERLINE, UP TO
66 FT AGL/965 FT MSL.
TREE 1950 FT FROM DER, 994 FT RIGHT OF CENTERLINE, 54 FT AGL/948 FT
MSL.
TREES BEGINNING 2591 FT FROM DER, 1100 FT RIGHT OF CENTERLINE, UP
MSL.
END PART 1 OF 3
ODP HECTOR INTL, FARGO, ND.
TO 74 FT AGL/969 FT MSL.
RWY 18: LIGHT POLE 4 FT FROM DER, 95 FT RIGHT OF CENTERLINE, 2 FT
AGL/900 FT MSL.
LIGHT POLES BEGINNING 5 FT FROM DER, 54 FT LEFT OF CENTERLINE, UP
TO 2 FT AGL/900 FT MSL.
LIGHT POLES, SIGN BEGINNING 9 FT FROM DER, 33 FT LEFT OF
CENTERLINE, UP TO 2 FT AGL/901 FT MSL.
LIGHT POLES BEGINNING 10 FT FROM DER, ON AND RIGHT OF CENTERLINE,
UP TO 2 FT AGL/901 FT MSL.
TRAVERSE WAY 536 FT FROM DER, 19 FT RIGHT OF CENTERLINE, 914 FT
MSL.
RWY 27: TRAVERSE WAYS, UTILITY BUILDING BEGINNING 9 FT FROM DER, 39
FT LEFT OF CENTERLINE, UP TO 1 FT AGL/897 FT MSL.
TRAVERSE WAYS, LIGHT POLE, SIGN BEGINNING 10 FT FROM DER, 50 FT
RIGHT OF CENTERLINE, UP TO 2 FT AGL/897 FT MSL.
UTILITY BUILDING 40 FT FROM DER, 125 FT RIGHT OF CENTERLINE, 4 FT
AGL/898 FT MSL.
TRAVERSE WAY BEGINNING 449 FT FROM DER, 478 FT RIGHT OF CENTERLINE,
UP TO 910 FT MSL.
TREE 2911 FT FROM DER, 943 FT LEFT OF CENTERLINE, 971 FT MSL.
MSL.
END PART 2 OF 3
ODP HECTOR INTL, FARGO, ND.
RWY 36: LIGHT POLE, TRAVERSE WAYS, ELECTRICAL SYSTEM, POLE
BEGINNING 9 FT FROM DER, 55 FT RIGHT OF CENTERLINE, UP TO 1 FT
AGL/901 FT MSL.
LIGHT POLES, TRAVERSE WAYS BEGINNING 9 FT FROM DER, 54 FT LEFT OF
CENTERLINE, UP TO 2 FT AGL/901 FT MSL.
TREE 2067 FT FROM DER, 984 FT LEFT OF CENTERLINE, 62 FT AGL/954 FT
MSL.
END PART 3 OF 3
4/8481
10/11/2024 17:33
05/22/2025 17:33
IAP HECTOR INTL, FARGO, ND.
RNAV (GPS) RWY 9, AMDT 1C...
LNAV/VNAV DA 1261/HAT 361 ALL CATS, VIS 1 ALL CATS. CIRCLING CAT A/B MDA 1400/HAA 499. TEMPORARY CRANE 1100 MSL 2829FT S OF RWY 9 (2023-AGL-14007-NRA). TEMPORARY CRANE 1098 MSL 3072FT S OF RWY 9 (2024-AGL-1785-NRA).
2410111733-2505221733EST
Start Date UTC
10/11/2024 17:33
End Date UTC
05/22/2025 17:33
Conditions
IAP HECTOR INTL, FARGO, ND.
RNAV (GPS) RWY 9, AMDT 1C...
LNAV/VNAV DA 1261/HAT 361 ALL CATS, VIS 1 ALL CATS. CIRCLING CAT A/B MDA 1400/HAA 499. TEMPORARY CRANE 1100 MSL 2829FT S OF RWY 9 (2023-AGL-14007-NRA). TEMPORARY CRANE 1098 MSL 3072FT S OF RWY 9 (2024-AGL-1785-NRA).
2410111733-2505221733EST
4/8482
10/11/2024 17:33
05/22/2025 17:33
IAP HECTOR INTL, FARGO, ND.
VOR RWY 36, ORIG-E...
STABS FIX MINIMUMS: CIRCLING CAT A/B MDA 1400/HAA 499. TEMPORARY CRANE 1100 MSL 4669FT NW OF RWY 36 (2023-AGL-14007-NRA). TEMPORARY CRANE 1098 MSL 4663FT NW OF RWY 36 (2024-AGL-1785-NRA).
2410111733-2505221733EST
Start Date UTC
10/11/2024 17:33
End Date UTC
05/22/2025 17:33
Conditions
IAP HECTOR INTL, FARGO, ND.
VOR RWY 36, ORIG-E...
STABS FIX MINIMUMS: CIRCLING CAT A/B MDA 1400/HAA 499. TEMPORARY CRANE 1100 MSL 4669FT NW OF RWY 36 (2023-AGL-14007-NRA). TEMPORARY CRANE 1098 MSL 4663FT NW OF RWY 36 (2024-AGL-1785-NRA).
2410111733-2505221733EST
4/8483
10/11/2024 17:33
05/22/2025 17:33
IAP HECTOR INTL, FARGO, ND.
ILS OR LOC RWY 18, ORIG-E...
ILS OR LOC RWY 36, AMDT 2A...
RNAV (GPS) RWY 18, AMDT 1C...
RNAV (GPS) RWY 27, AMDT 1C...
CIRCLING CAT A/B MDA 1400/HAA 499. TEMPORARY CRANE 1100 MSL 2359FT W OF FAR AIRPORT (2023-AGL-14007-NRA). TEMPORARY CRANE 1098 MSL 2896FT W OF FAR AIRPORT (2024-AGL-1785-NRA).
2410111733-2505221733EST
Start Date UTC
10/11/2024 17:33
End Date UTC
05/22/2025 17:33
Conditions
IAP HECTOR INTL, FARGO, ND.
ILS OR LOC RWY 18, ORIG-E...
ILS OR LOC RWY 36, AMDT 2A...
RNAV (GPS) RWY 18, AMDT 1C...
RNAV (GPS) RWY 27, AMDT 1C...
CIRCLING CAT A/B MDA 1400/HAA 499. TEMPORARY CRANE 1100 MSL 2359FT W OF FAR AIRPORT (2023-AGL-14007-NRA). TEMPORARY CRANE 1098 MSL 2896FT W OF FAR AIRPORT (2024-AGL-1785-NRA).
2410111733-2505221733EST
4/6922
07/03/2024 12:02
01/31/2025 12:02
ODP HECTOR INTL, FARGO, ND.
TAKEOFF MINIMUMS AND (OBSTACLE) DEPARTURE PROCEDURES AMDT 4A...
ADD TAKEOFF OBSTACLE NOTES: RWY 9, TEMPORARY CRANE 3307FT FROM DER, 598FT RIGHT OF CENTERLINE, 91FT AGL/985FT MSL (2023-AGL-12828-OE). ALL OTHER DATA REMAINS AS PUBLISHED. 2407031202-2501311202EST
Start Date UTC
07/03/2024 12:02
End Date UTC
01/31/2025 12:02
Conditions
ODP HECTOR INTL, FARGO, ND.
TAKEOFF MINIMUMS AND (OBSTACLE) DEPARTURE PROCEDURES AMDT 4A...
ADD TAKEOFF OBSTACLE NOTES: RWY 9, TEMPORARY CRANE 3307FT FROM DER, 598FT RIGHT OF CENTERLINE, 91FT AGL/985FT MSL (2023-AGL-12828-OE). ALL OTHER DATA REMAINS AS PUBLISHED. 2407031202-2501311202EST
11/032
11/06/2024 12:00
11/29/2024 01:00
RWY 13 CLSD TO LDG WED THU FRI MON TUE 1200-0100
Start Date UTC
11/06/2024 12:00
End Date UTC
11/29/2024 01:00
Conditions
RWY 13 CLSD TO LDG WED THU FRI MON TUE 1200-0100
11/035
11/06/2024 12:00
11/29/2024 01:00
RWY 31 CLSD TO TKOF WED THU FRI MON TUE 1200-0100
Start Date UTC
11/06/2024 12:00
End Date UTC
11/29/2024 01:00
Conditions
RWY 31 CLSD TO TKOF WED THU FRI MON TUE 1200-0100
10/116
10/31/2024 20:49
11/21/2024 21:00
RWY 09 RWY END ID LGT NOT STD
Start Date UTC
10/31/2024 20:49
End Date UTC
11/21/2024 21:00
Conditions
RWY 09 RWY END ID LGT NOT STD
11/037
11/05/2024 21:35
11/20/2024 21:00
TWY C3 WIP CONST ADJ EAST EDGE LGTD AND
BARRICADED
Start Date UTC
11/05/2024 21:35
End Date UTC
11/20/2024 21:00
Conditions
TWY C3 WIP CONST ADJ EAST EDGE LGTD AND
BARRICADED
11/030
11/04/2024 19:47
11/15/2024 21:00
TWY B BTN SOUTH GA RAMP AND TWY M WIP CONST ADJ EAST EDGE
LGTD AND BARRICADED
Start Date UTC
11/04/2024 19:47
End Date UTC
11/15/2024 21:00
Conditions
TWY B BTN SOUTH GA RAMP AND TWY M WIP CONST ADJ EAST EDGE
LGTD AND BARRICADED